Gulf offshore supply vessels

Four platform supply vessels converted to diesel-electric propulsion with batteries, using eight DNV-approved motors built in Jebel Ali.

Electric propulsion motors in a ship’s engine room

The result

less fuel burned
22%
Average across the four vessels
less CO₂ a year
6,800 t
Fleet total, operator’s figures
propulsion motors
8
1.8 MW each, water-cooled
weeks in dry dock
6
Per vessel, as planned

The challenge

The operator’s four supply vessels spent much of their time holding position beside offshore platforms in the Gulf, with diesel engines running far below their efficient load.

Each conversion had to fit inside a six-week dry dock slot, and the motors had to fit the existing shaft lines and engine room openings.

What we did

  1. Engineering

    3D scans of each engine room and a motor designed to pass through the existing hatch.

  2. Motors

    Eight 1.8 MW water-cooled propulsion motors, built and type-tested in Jebel Ali.

  3. Installation

    Our marine team on board throughout each dry dock, working with the yard.

  4. Sea trials

    Trials and DNV survey for each vessel, then a remote monitoring link to Jebel Ali.

On site

  • Electric propulsion motors in a ship’s engine room
    Offshore vessel operator, Abu Dhabi, 2025
  • Offshore supply vessel on calm water in the Gulf
    Our marine team on board throughout each dry dock, working with the yard.
Norvik’s marine engineers lived in the dry dock with us for six weeks. Fuel use across the four ships is down by more than a fifth.
Rajesh NairTechnical superintendent, offshore vessel operator, Abu Dhabi

Planning something similar?

Tell us the duty and the site. We’ll put you in touch with the engineers who did this job.

Chat on WhatsApp

Cookie preferences

Cookie policy