Oil and gas · Pipeline operator, Oman · 2025

Al Wusta pipeline pump station

Three 2.5 MW drive systems for a crude oil pipeline pump station, delivered as a tested drive house and running nine days early.

Pipeline pumping station in flat desert, seen from above

The result

pump station availability
99.2%
First twelve months of operation
less energy
18%
Against throttled fixed-speed pumps on the old station
days early
9
First oil through the station
design ambient
50 °C
With full output, no derating

The challenge

A new pump station on a 300 km crude oil pipeline had to restart at full flow after any stop, in 50 °C summer heat and fine sand, five hours’ drive from the nearest town.

The operator wanted one supplier for motors, drives and the drive house, and as little electrical work on site as possible.

What we did

  1. Drive train design

    Three 2.5 MW 3.3 kV Ex db flameproof motors, sized for full-flow restarts and load sharing between pumps.

  2. Drive house

    Medium voltage drives, transformers and controls in one 18-metre steel building, cooled for 50 °C.

  3. System test

    Full-power test of all three drive trains in Jebel Ali, witnessed by the operator’s engineers.

  4. Site and support

    Commissioned in five days by our Muscat team, who now hold critical spares on site.

On site

  • Pipeline pumping station in flat desert, seen from above
    Pipeline operator, Oman, 2025
  • Inside the drive house: a row of tall grey drive cabinets
    Full-power test of all three drive trains in Jebel Ali, witnessed by the operator’s engineers.
The drive house arrived tested, wired and ready to plug in. We were pumping crude nine days ahead of plan.
Salim Al HinaiProject director, pipeline operator, Oman

Planning something similar?

Tell us the duty and the site. We’ll put you in touch with the engineers who did this job.

Chat on WhatsApp