Water · Water and power utility, UAE · 2026

Fujairah seawater desalination plant

24 seawater pump motors replaced with IE5 motors and drives, two pump trains a weekend, while the plant kept supplying 380,000 people.

Row of pumps and motors in the Fujairah pump hall

The result

less pumping energy
31%
Measured over the first six months
saved every year
3.2 GWh
About AED 1.1 million at 2026 tariffs
years to pay back
2.6
Including drives and installation
hours of lost supply
0
Across twelve changeover weekends

The challenge

The seawater pump hall at Fujairah ran on 24 fixed-speed motors installed in 1998. They were reliable, but inefficient, and flow was controlled by throttling valves that wasted a third of the energy they used.

The plant supplies 380,000 people and could not be taken out of service. Any changeover had to fit inside a weekend window in the cooler months, with every pump back in service by 5 a.m. on Monday.

What we did

  1. Survey and design

    Laser survey of every pump base, and a harmonic study of the plant supply.

  2. Build and test

    24 NX-series 400 kW IE5 motors and 24 drives, run together on our Jebel Ali test bay.

  3. Weekend changeovers

    Two pump trains per weekend, with our crew on site from Friday 6 p.m. to Monday 5 a.m.

  4. Handover

    Energy monitoring for six months and a five-year service agreement.

On site

  • Row of pumps and motors in the Fujairah pump hall
    Water and power utility, UAE, 2026
  • Engineers lowering a new motor onto a pump with a gantry crane
    Two pump trains per weekend, with our crew on site from Friday 6 p.m. to Monday 5 a.m.
Twenty-four motors changed over twelve weekends and not one hour of lost supply. The energy figures came in better than the business case.
Saeed Al DhaheriAsset manager, water and power utility (Fujairah project)